外研版 职业模块 ▪ 工科类
/Unit 2 : Work to the Schedule /
第3课时 Extended activities & Culture Corner
Learning objectives
knowledge objectives
ability objectives
emotional objectives
write a simple production plan;
talk about your work schedule;
describe different timetables.
Task 1
Owen works in a printing and packaging company. Help him put the work procedures in the correct order.
A. packing B. delivery C. production
D. material selection E. design
E
D
C
B
A
Task 2
Owen is working on a new project. Read his notes and circle the key information.
Task 3
Here is Owen’s project schedule. Do you think it is in line with his notes? Why or why not?
No, it is not in line with Owen’s notes. According to his notes, it takes one day to pack and two days to deliver the products. However, Owen’s project schedule shows that packing takes two days and delivery takes one day.
Task 4
Owen might face various challenges while working on the project. List some and work with a partner to find solutions.
Task 5
1. What is Gantt chart?
2. What are the benefits of Gantt chart?
Some people may have never heard of a Gantt chart (甘特图). Simply put, a Gantt chart is a visual reminder of tasks you have scheduled over a period of time.
On a Gantt chart you can easily see:
□ the start date of the project;
□ what the project tasks are;
□ when the tasks start and finish;
□ how long each task will take;
□ how the tasks are grouped together, overlap (交叉) and link with each other;
□ the finish date of the project.
Many people are used to creating task lists in Excel or other spreadsheet (电子表格) tools. It works fine when you’re creating a list of things for one person to view. But when you want to add more people to the activity, creating a Gantt chart will be a more effective way of working. With it, you can visualise (设想) the entire project, see how tasks are connected, keep everyone on the same page and know who’s busy and who isn’t.
Today, Gantt charts are the prefe